What the county is buying
by RFPFinder from the notice and attachments; the solicitation governsTift County Board of Commissioners seeks construction of water, street and drainage improvements for West Phillipsburg Phase 2, including roadway, storm drainage and water main replacement. Work must be completed within 180 days to substantial completion; award method and evaluation criteria are not stated.
Scope
- 3,600 linear feet of 20-foot-wide urban roadway with curb, gutter and asphalt
- 1,230 linear feet of 2-inch PVC water main replacement and storm drainage infrastructure
How to get the bid documents
- Download the 1 document below (no portal account needed)
- Check the submission requirements in the compliance checklist
- Submit as the notice directs before 11:00 AM ET on Nov 17
Details
- Place of performance
- Georgia
- Buyer type
- County
- Notice type
- Non-State Agency
- Solicitation no.
- PE-77648-NONST-2027-000000031
- Category
- Construction · beta
- Delivery location
- West Phillipsburg, Georgia from notice
- Period of performance
- 180 consecutive calendar days to substantial completion; 194 consecutive calendar days to contract c from notice
- Local presence
- Not required
- Amendments
- None since Oct 16
Not stated in the notice: estimated value, contract type. Check the bid documents.
Contact details from the source notice. Contact the buyer only about this solicitation.
Key dates
Change log
verified Fri, Oct 16 · 2:17 PM ETNo amendments since posting on Fri, Oct 16; verified Fri, Oct 16 · 2:17 PM ET.
Report a problem
Notice as published
Water, Street & Drainage Improvements - W Phillipsburg Phase 2
The work to be done shall consist of furnishing all labor, materials and equipment necessary to construct the proposed Water, Street & Drainage Improvements to serve the West Phillipsburg Community Phase 2 as shown on the construction drawings. In general, construction consists of +/- 3,600 linear feet of twenty-foot-wide urban roadway including curb and gutter, storm drainage pipe and boxes, base and asphalt, +/- 1,230 linear feet of 2-inch PVC water main replacement with the transfer of existing water services, fire hydrants, etc., and all associated measures for the complete project. Time allotted for completion of work is 180 consecutive calendar days to substantial completion.
Work shall be complete and ready for contract close-out with 194 consecutive calendar days. All work shall be completed in accordance with the plans and specifications. The work will be awarded in one
- Contract.
Similar open RFPs in Georgia
same contracting officeListing collected from Georgia DOAS - Georgia Procurement Registry (GPR) / Team Georgia Marketplace. Always confirm requirements in the original solicitation before you bid.